PERT/SD Question Submitted by Julbrown31 on Tue, 04/16/2013 - 03:34 Forums: General Discussion 27. A project manager made 3-point estimates on a critical path and found the following results: Assuming ±3 sigma precision level for each estimate, what is the standard deviation of the allover path?