another time mgmt ques
Submitted by vivek919 on Fri, 04/12/2013 - 02:38
Forums:
| Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
What is the minimum total duration between the milestones A and B? | ||