problem in risk management knowledge area
A company has to make a choice between 2 projects, because available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. The first project is a process optimization which would result in a cost reduction of $120,000 per year. The benefit would be acheived immediately after the end of the project
The second project would be the development of a new product which could produce the following net profits after the end of the project
1year $15000
2 year $125000
3 year $220000