Questions on Opportunity Cost
Submitted by Reeta on Tue, 03/05/2013 - 05:21
Forums:
You have to select between four projects. Project A with Net Present value (NPV) of
$100,000, Project B with NPV of $70,000, Project C with Net Present value (NPV) of
$105,000 and Project D with NPV of $95,000. What is the opportunity cost of selecting
Project C ?