Planning Process: SCOPE Baseline vs SCOPE Statement
Submitted by JanaDee on Wed, 02/13/2013 - 16:26
Forums:
I understand "SCOPE Baseline" is created in "Create WBS" process, where "Project Scope Statement" is input from "Define Process". And I also understand that "Scope Statement" (Assumptions, Constraints, Stakeholder Analysis etc) is included in "Scope Baseline".
In Project Time Management, "Define Activities" process, i will use "Scope Baseline" as Input but will have "Project Scope statement" as output.