I got this question on a practice exam yesterday and I cant seem to find a solution on how to correctly solve this type question/s, if asked on the real PMP exam... any help is greatly appreciated.
Question> you are the project manager and in your project the overtime associated with the execution effort of a project are estimated at 180 hours and 270 hours with a probability 0.2. what is the monetary value of the amount of overtime?
Choices are:
A) 315
B) 231
C) 236