What should be correct answer=
Q.Payola is working in a project to replace all the old workstations in the organization with new ones. The new workstations have arrived and her team has started to unpack the new ones while the old ones are still being taken out of the organization. This is an example of _____
A.adding lag
B.crashing
C.what if scenario analysis
D.fast tracking