Oliverlehmann Question 94 Explanation Required

Together with your team, you applied three-point estimation on a critical path which consists of two activities. 
The following duration uncertainties are all calculated assuming a ±3sigma confidence interval. 
The duration uncertainty—defined as pessimistic minus optimistic estimate—of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths.
What is the duration uncertainty of the entire path?
 
A) 21 days
B) 30 days
C) 42 days