Crashing Question - What is the correct answer along with reason

Five tasks have to be completed one after another in your project. The Contract with your Sponsor contains very strict penalties for delays. The schedule reveals that the project has a negative float of three months, which of the following task(s) should be crashed to bring the project on schedule?