Need Clarification - Lag example in PMBOK Fifth edition
Submitted by hemald on Thu, 08/13/2015 - 09:23
Forums:
Hello
On PMBOK Fifth Edition Page 158, there is example of lag.
Activity 1 (Preceding activity) = Write Draft
Activity 2 (Successor activity)= Edit Draft
Activity 1 is connected to Activity 2 by Start to Start with 15 Days Lag
Now I am not understanding, why PMBOK has mentioned SS - 15 Days (Lag).
Why PMBOK has not mentioned SS + 15 Days (Lag)
Please explain this.
Thanks
