Time management question
Submitted by NISHA on Fri, 06/26/2015 - 19:36
Forums:
Hey Guys..
Please help me to answer this question.
- A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
- Finish-to-Start
- Start-to-Finish
- Start-to-Start
- Finish-to-Finish
Thanks
Nisha