Question on accepted risk
Submitted by mwaqas on Tue, 04/21/2015 - 07:07
Forums:
Q: While monitoring project risk, you find that an accepted risk is going to occur. Which of the following will you use to develop response?
A: Risk response plan
B: Fallback plan
C: Mitigation plan
D: Risk register
Two seperate sources have two different answers so it is confusing.