Im confused in what happens first. 

Your team has recommended a change to the Verify Scope process. What’s the first thing you should do?
 
(1) Analyze the change versus the Project Management plan to see what its impact will be.
(2) Write up a change request
 
I chose 2 considering that only after I write up a request I should analyze the impact. What is the correct process flow here for a change request.