interesting PMP question to discuss
Submitted by sch_oliver2000 on Fri, 09/12/2014 - 13:51
Forums:
Hallo everybody,
I faced the folllowing PMP question and I have difficulty to understand its answer:
The Question:
In order to implement a quality assurance activity to supplment exisiting quality control activities, which of the following is the right tool for this purpose?
a)Benchmarking
b)Run Chart
c)Expert Judgement
d)Statistical Sampling