Zero value of contingency reserve?
Submitted by PMP Fighter on Fri, 07/04/2014 - 04:00
Forums:
A project manager is trying to plan for a contingency reserve as part of the cost estimates for the project. Which of these would be an incorrect way to plan for contingency reserves?
A Start the project with a zero value for contingency reserve.
B Plan for contingency reserve as a fixed number.
C Plan for contingency reserve as a percentage of the estimated cost.
D Use quantitative analysis methods to arrive at the contingency reserve.
The answer is A,