Can someone help me to get the PTA for this question
Submitted by Binay Anand on Tue, 06/10/2014 - 04:44
Forums:
Target cost:$1,000,000Target contractor fee:$100,000Cost benefit sharing ratio:80%/20%Price ceiling: $1,200,000
In a project, a cost incentive contract has been awarded to a contractor with the following parameters: What is the point of total assumption (PTA, breakpoint) of the project?46
o $1,000,000
o $1,100,000
o $1,125,000
o $1,200,000