TCPI Calculation

Please help me in calculating the TCPI

For your project, find the to-complete performance index (TCPI) based on the given data:
Budget at completion of the project = 700,000
Cost variance of the project = 25,000
Earned value of the project = 200,000
Estimate to Complete has now been revised to 425,000
 
  Choice 1  0.9   
  Choice 2  1.176 
  Choice 3  1.5  
  Choice 4  -1.5

Thanks

Jai

 Here ETC = 425000 is given

means fund available = 425000, 

work remained = BAC - EV (at point of time of completed work) = 700000 - 200000 = 500000

TCPI = work remained / fund available = 500000/425000 = 1.176

 

crushPMP's picture

Answer is Choice 2


CV = EV - AC
25 = 200 - AC
AC = 175

EAC = ETC + AC
EAC = 425 + 175
EAC = 600


TCPI = (BAC - EV) / (EAC - AC)
TCPI = (700 - 200) / (600 - 175)
TCPI = 500/425
TCPI = 1.17647058