TCPI Calculation
Submitted by Jgrind07 on Thu, 05/02/2013 - 03:21
Please help me in calculating the TCPI
For your project, find the to-complete performance index (TCPI) based on the given data:
Budget at completion of the project = 700,000
Cost variance of the project = 25,000
Earned value of the project = 200,000
Estimate to Complete has now been revised to 425,000
Choice 1 0.9
Choice 2 1.176
Choice 3 1.5
Choice 4 -1.5
Thanks
Jai
Forums:


sspawar
Thu, 05/02/2013 - 04:25
Permalink
Here ETC = 425000 is
Here ETC = 425000 is given
means fund available = 425000,
work remained = BAC - EV (at point of time of completed work) = 700000 - 200000 = 500000
TCPI = work remained / fund available = 500000/425000 = 1.176
crushPMP
Thu, 05/02/2013 - 15:19
Permalink
Answer is Choice 2 CV = EV -
Answer is Choice 2
CV = EV - AC
25 = 200 - AC
AC = 175
EAC = ETC + AC
EAC = 425 + 175
EAC = 600
TCPI = (BAC - EV) / (EAC - AC)
TCPI = (700 - 200) / (600 - 175)
TCPI = 500/425
TCPI = 1.17647058