You just created the following network logic diagram to describe the planned flow of activities for your project which will start tomorrow:
Which potential inconsistency in the diagram should you solve right now? |
||
| Activity E is open ended ( a "dangle") in relation to the finish milestone path convergence. | ||
| Activity F is open ended in relation to the path divergence after the start milestone. | ||
| You cannot calculate a critical path when lags and/or leads are calculated in percent. | ||
| Activities E to F need another task drawn as a hammock to calculate level of effort. | ||
The correct answer is Fiorst choice. Can somebody explain me?