Today's Fiver
All,
Please see below for my daily Fivers. BTW, I got ALL wrong. Here we go:
1. A foreign construction company working on a road project will need to be familiar with local rules and regulations to minimize estimating mistakes. Likewise, a software development dev team must be well versed in the largest technologies so that programming activities can be identified correctly and the budget allocated accurately. As such, it’s important that Estimate Activity Resources process is coordinated with the following -------------------------- process.
A. Estimate Cost
B. Control Schedule
C. Perform QC
D. Administer Procurements
2. Your initial schedule requires more resources in November and January than are available to you. The process of adjusting your schedule to accommodate these constraints is called which of the following?
A. Fast Tracking or crashing tasks
B. Resource leveling
C. Resource negotiation
D. Schedule finalization
3. Which statement is true about crashing? A. It is effective only for the tasks on the critical path. B. It is the preferred approach to dealing with schedule problems because it almost always offers a viable solution C. It actually does not increase risk, although it normally increases cost D. The method is based on adjusting people resources rather than materials or equipment 4. Which graphical representation of the project schedule typically lists the activities on the left, the date across the top, and the duration of each activity displayed as horizontal bars whose lengths are relative to the duration of the activities? A. Milestone Chart B. Gantt Chart C. Project network diagram D. Resource loading chart 5. In performance reports related to schedule performance, which is unique to activities? A. Actual Start Date B. Baseline Finish date C. Baseline Start Date D. Forecast remaining time Warmly, KK... :) :) :)


karthik21
Thu, 07/26/2012 - 09:31
Permalink
My response
1.B
avradip.paul
Thu, 07/26/2012 - 09:33
Permalink
My answers are, 1. A 2. B 3.
My answers are,
1. A
2. B
3. A
4. B
5. D (Did not understand the qs properly)
Let me know know the correct answers.
Ramana_99
Thu, 07/26/2012 - 09:56
Permalink
My Answers...
- Ramana
krantikumar50
Thu, 07/26/2012 - 11:30
Permalink
Why?
What and why are you confused on D?
Warmly, KK...
karthik21
Thu, 07/26/2012 - 11:59
Permalink
Share the answers KK.. looks
Share the answers KK.. looks like we dont seem to have a symmetry with the responses
krantikumar50
Thu, 07/26/2012 - 12:13
Permalink
Hi
Hi Karthik,
Mr Avradip Paul is 100% correct and still he was not sure on last question. That is why I asked him.
However, his answer or for that matter all his answers are true.
Mr Paul is, for sure, studying pretty well :) :) : )
Posting the next 5 questions soon :)
Warmly, KK....
Jay22
Thu, 07/26/2012 - 12:54
Permalink
Hi KK, where are you getting
Hi KK, where are you getting these questions from?
krantikumar50
Thu, 07/26/2012 - 12:57
Permalink
Ping me...
Ping me when you are connected on gmail....
RaviDatt
Thu, 07/26/2012 - 14:37
Permalink
My Answer would have
My Answer would have been:
A
B
C
B
D (guess) Need explaination ?
Thanks,
RD