unexpected answers
1. Your project is mid-way through a delivery schedule. As project manager, you want to understand how much work is left. Which is the most accurate way to determine the remaining work to be done by the project team?
A. Future analysis
B. Rolling wave method
C. Earned Value Technique
D. A Manual forecast
2. Which of these are not inputs to the Determine Budgets process?
A. Future analysis Cost baseline, Requirements traceability matrix
B. Project schedule, contracts
C. Basis of estimates, Activity cost estimates
D. Project schedule, Resource calendars


saurabh24jain
Tue, 06/19/2012 - 09:51
Permalink
Answers ?
Pls provide answers ?
karthik21
Tue, 06/19/2012 - 10:09
Permalink
IS the answer A and A for
IS the answer A and A for both questions ?
krantikumar50
Tue, 06/19/2012 - 21:10
Permalink
Answers
Respected Pawarji Sir,
Answers are D and A.
Thanks,
KK...
sspawar
Wed, 06/20/2012 - 16:29
Permalink
yes D & A
yes D & A