unidentified risk discovered
Submitted by vijayavadrevu on Wed, 05/29/2013 - 20:17
You are the project manager for a new software development project. A previously unidentified risk is discovered when the project is nearing completion. You realize that this risk may adversely impact the project`s overall ability to deliver. As a project manager, what step do you take FIRST?
- Perform Quantitative Risk Analysis
- Inform the project sponsor and the stakeholders about the potential impact of the risk on the project
- Perform Qualitative Risk Analysis
- Mitigate the risk to reduce its impact
Forums:


Rmandal
Wed, 05/29/2013 - 20:40
Permalink
Option 3
Option 3
Vishwanath
Wed, 05/29/2013 - 20:46
Permalink
3
3?
DonJuanin
Wed, 05/29/2013 - 20:51
Permalink
3
3
aah, whenever new risk identified FIRST of all qualify them.. ( Perform Qualitative Analysis).
sanskrit
Thu, 05/30/2013 - 00:30
Permalink
3
3 Perform Qualitative Risk Analysis
vijayavadrevu
Thu, 05/30/2013 - 05:59
Permalink
Yes, 3 is the right option
Yes, 3 is the right option