A project team is in the planning stage and they have completed creating Work breakdown structure for the project. Which of the following process can they start NEXT?

Options:
A. Define Activity
B. Estimate Cost
C. Determine Budget

D. All of the above

What should be the answer. The source says D, which I feel is incorrect, and my answer is A. Any thoughts???

0
Your rating: None

 It should be define activity

 It should be define activity