Which process to update PM plan?
Submitted by bluesky7804 on Sun, 12/22/2013 - 14:11
The changes related to cost baseline were approved by CCB. You are now updating the project management plan to incorporate the changes. In which project management process would this be done?
A. Direct and Manage Project Work
B. Perform Integrated Change Control
C. Monitor and Control Project Work
D. Control Cost
Forums:


jagadeesh2k3
Sun, 12/22/2013 - 15:19
Permalink
option B
I would go with perform integrated change control as based on this cost change, there would be other changes required. Please tell me the source of question.
bluesky7804
Sun, 12/22/2013 - 19:35
Permalink
The question was from myself, I am really confused by "Update PM
I agree with your answer, but am still confused why it is not "Control Cost" or "Manage project or Work" process, where update PM Plan is also one of the outputs.
delfa
Tue, 12/24/2013 - 05:59
Permalink
I agree with B as change
I agree with B as change happened and also the baseline updated this activity will be happened integrated change
danielkoshy
Fri, 12/27/2013 - 13:34
Permalink
I think
As I understand it, the questions is asking in which process would the approved change take place.I would go with : Direct and Manage project work.(source Pmbok pg82 4.3.1.2)
krishpill
Mon, 12/30/2013 - 19:03
Permalink
Direct and Manage project work
Answer - A- Direct and Manage project work.Explained clearly in PMBOK page 82.