3 point estimate
James has been managing a hotel construction project in a busy street. He is in the process of estimating activity durations for building walls and calculates the most likely estimate as 15 days. However, the work may be delayed and could take up to 18 days if less experienced construction workers are used to build the walls. But, the engineer in- charge of the work estimates the duration as 8 days when prefabricated material is used. What is the expected duration of building walls using the three-point estimate, if the engineer's estimation is assumed correct?
A) 12 days
B) 11days
C) 15 days
D) 14 days
Applying the formula, PERT = 14.33 days. Hence chosen option C. Whereas answer is given as D. If such problems come up, should be round off or not? i.e., like 14.33 to 15


sanskrit
Tue, 05/21/2013 - 00:08
Permalink
I will say to use regular rounding
I will say to use regular rounding, which mean if it is less than 0.5 than foor if it is gretater than 0.5 than ceiling. So if it is 14.49 than round it to 14 if its is 14.51 then 15
cnppmp
Tue, 05/21/2013 - 06:26
Permalink
Also for 14.50 as well 15 be
Also for 14.50 as well 15 be picked
Regards CNP
vijayavadrevu
Tue, 05/21/2013 - 09:44
Permalink
Thank You!!!