Explanation Needed...
Submitted by krantikumar50 on Sat, 03/24/2012 - 19:02
Hi All:
If a project is over, how come its SPI and CPI or CV and SV would be at least 1.
I am not understnading it. Can it be explained please.
Thanks,
KK
Forums:


pmp_man
Sat, 03/24/2012 - 19:19
Permalink
Depends upon the project status
SPI and SV has to do with schedule and CPI and CV is associated with the cost. You can have any values (<1 or >1) of these at any project phases depending upon the project status. Hence, look at the scenario that’s given and not its number to decide the project phase.