***Activity Duration - Calculation ***
Submitted by sam_jain on Mon, 05/07/2012 - 05:53
| Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
What is the minimum total duration between the milestones A and B? |
||
| 36 days | ||
| 37 days | ||
| 39 days | ||
| 42 days | ||
Per my calculation - answer is 42 days.
But correct answer is 37 days .
Please advise.
Forums:



shaikfromriyadh
Mon, 05/07/2012 - 08:31
Permalink
Activity Duration Calculation
Given: Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
The calculation is as below:
Activity 3 is finish to finish. Since the lead is two days. The activity 3 will complete 2 days before activity 2. Activity 4 will start after activity 3
=Activity 1 + Activity 2 - 2 days lead + 3days lag of activity4 + Activity 4
=20 + 10 - 2 + 3+ 6
= 37 days.
sam_jain
Mon, 05/07/2012 - 14:05
Permalink
My calculation is different...
Thanks for the details..
But my understanding is as follows:-
Activity 3 is finish to finish --> It means Activity 2 (Predecessor activity) should finish before finsh of successor activity ( Activity 3)
Since the Lead time for Activity 3 is 2 days , so Activity 3 can start 2 days before the finish date of Activity 2.
=Activity 1 + Activity 2+ Activity 3 with 2 days lead + Activity4 with 3days lag
=20 + 10+ (5-2) + (6+3)
= 42 days.
Regards,
Sam
sspawar
Mon, 05/07/2012 - 15:04
Permalink
Activity 3 is finished 2 days
Activity 3 is finished 2 days early the finish of activity 2. =FF-2
Since Activity 4 is successor of activity 3 hence activity 4 will start 2 days early then activity 2 will get finish.
duration of activty 3 wil be thus not come in calculation.
20 (a1) + (10-2)(a2/a3) + 3 (LAG of a4) + 6 (a4) = 37
sam_jain
Tue, 05/08/2012 - 02:21
Permalink
Great Explanation !!
Thanks SSPawar and ShaikfromRiyadh
sunitaPMP
Mon, 01/21/2013 - 06:33
Permalink
I have a doubt here.Can we
I have a doubt here.
Can we have the relation FS -2 between Act 2 and Act 3 instead of FF - 2 ? then how the calculation would be?
peeyushm
Thu, 01/31/2013 - 11:35
Permalink
If its FS-2 then it shoudl
If its FS-2 then it shoudl be
20 + 10 + (5-2) + (6+3) = 42
Ohana
Mon, 01/21/2013 - 02:02
Permalink
How do you read the chart
Can you please interpet how your read this chart since this is the first time I have seen a PERT with FF.
Thanks
virender.bhat
Sat, 08/12/2017 - 09:33
Permalink
Which part of the question
Which part of the question says that Activity 3 is FF
jessicabrook (not verified)
Fri, 03/29/2013 - 09:07
Permalink
whatiswebsdesign.com
whatiswebsdesign.com Well, this article really is hard to find ah, not only do the rich content wonderful interesting, and rich administrative levels feels very logical, the truth of the paper is very clear, no hidden a little truth, very delicate have send. I\’ll read more seriously.
Raju8448
Sat, 10/04/2014 - 11:54
Permalink
Leads and lags
what would be the result if it is SS-2 days between Activity 2 and activity 3.The same what it would be for SS+2 days.