Question from Oliver Lehmann (www.oliverlehmann.com)
Submitted by Hylton on Mon, 07/09/2012 - 22:38
Your project exceeded costs in the past caused by an underestimation of
resource costs in the cost baseline:
PV: $1,200,000, EV: $1,000,000, AC: $1,200,000
You expect the underestimation to influence the future as much as it did in the
past.
If the value of the remaining work (BAC – EV) is at $1,000,000, what should be
your new EAC (estimate at completion)?
o $1,800,000
o $2,000,000
o $2,200,000
o $2,400,000
Answer sheet has 4 as the answer.
In my opinion:
ETC (BAC - EV) = 1 000 000
AC = 1 200 000
EAC = AC + ETC = 1 000 000 + 1 200 000 = 2 200 000 ( Not correct accoridng to answer sheet)
Forums:


sspawar
Tue, 07/10/2012 - 00:03
Permalink
ETC = remained BAC/CPI
actually here as per trend analysis
CPI = EV/AC = 100000/120000 =5/6
EAC for remaining work will be ETC = BACremained/CPI = 100000/5/6
EAC = AC+ETC = 120000 + 120000
Hylton
Tue, 07/10/2012 - 01:27
Permalink
thanks ss
thanks ss
Hylton
Tue, 07/10/2012 - 01:32
Permalink
Question
Hi SS
How do you get to BAC as 1 000 000?
sspawar
Tue, 07/10/2012 - 02:03
Permalink
it is given
If the value of the remaining work (BAC – EV) is at $1,000,000, what should be -----