KK, a question
Submitted by sspawar on Thu, 07/12/2012 - 08:24
You are a project manager and sponsor has given you a liberty to choose a project among A and B and You have preferred A because it has
A. Higher IRR, NPV, Opportunity cost, and BCR
B. Higher IRR, NPV, payback, and BCR
C. Higher NPV, ROI, and BCR
D. Higher EVA , Opportunity cost, and payback
Forums:


Zephyr
Thu, 07/12/2012 - 08:41
Permalink
Answer is 'C' - NPV, IRR,
Answer is 'C' - NPV, IRR, BCR should be high, Payback period should be less, and oppurtunity cost does not ideally qualify as a criteria for project selection. Please advice.
rrbhandare
Thu, 07/12/2012 - 08:59
Permalink
Answer should be option
Answer should be option "C".
Regards
Rajendra
krantikumar50
Thu, 07/12/2012 - 09:05
Permalink
Jawaab...
Respected Pawarji Sir,
The answer is an obvious "C".
I dont think opportunity cost is even taken for consideration. That takes out option A and D. am learning the art of elimination, thanks to you respected Pawarji Sir.
Now, we have B and C. So, I would go with "C", respected Pawarji Sir.
Rest on you to unravel the mystery respected Pawarji Sir.
Warmly, KK....
sspawar
Thu, 07/12/2012 - 11:55
Permalink
yes
you are right
opp cost should not be higher- because it is cost of left over option that is project B.
if project A has higher opp cost means cost of project A is lower than cost of B, project B is better.
paybacktime should not be higher