domain initiation
You have just been assigned as the project manager for a research project that your company has been awarded. As part of the execution of this project for your customer, you will be carrying out major statistical research in all of the major cities in your country.
Your project sponsor, who is also the CEO of your company has asked you to prepare the Project Charter and get it signed by him. However, you discover that the project Statement of Work (SOW) does not exist in a formal, documented form. This is a very important input to the Develop Project Charter process. Where can you get the formal, documented project Statement of Work?
A You should create the project Statement of Work yourself since you are the project manager.
B You should look for the project Statement of Work in your organizational process assets.
C You should ask your project sponsor to provide you the project Statement of Work.
D You should ask your customer to provide you the project Statement of Work.


karthik21
Sun, 07/22/2012 - 18:25
Permalink
My answer
This question looks like a case of source to project SOW. Based on the options , I could strike off A and B. OF C and D I go with C.
My answer is "C"
RaviDatt
Sun, 07/22/2012 - 19:20
Permalink
In this case Contract with
In this case Contract with customer would act as a SOW.
I will go with D.
ameenhaqqi
Sun, 07/22/2012 - 21:14
Permalink
I would go with option B. SOW
I would go with option B. SOW template can be found in OPA and we should look for it in OPA first.
krantikumar50
Mon, 07/23/2012 - 01:50
Permalink
I would go with....
I would go with "B" since SoW can be found in OPAs.
Warmly, KK....
Manjukanwar
Mon, 07/23/2012 - 02:08
Permalink
I would go with D: ask the
I would go with D: ask the customer to provide you the SOW as you are doing the project for the customer.
Thanks,
MK
aliweb
Mon, 07/23/2012 - 03:06
Permalink
D is the correct answer.
D is the correct answer.