DEVELOPING THE PROJECT BUDGET
1. The ----------------------- is established using the WBS and its associated Control Accounts.
2. The Control Account also has a unique identifier that is linked to the organization’s accounting system, sometimes known as a ----------------.
3. -------------------- should be completed early in the project to help estimate the costs.
4. The following 3 additional tools can be used to predict the potential financial performance of the project’s product, service, or result.---------------------
5. A project’s cost performance baseline has a/an --------------- shape.
6. ------------------ entails providing the information in the correct format to the right audience in a timely manner.
7. What is the communication channel formula? -----------------------------
8. The lines that connect the communication nodes are also known as ----------
9. The ------------------- addresses the communication needs of the project SH.
10. What is a PMB? -----------------------------------------------


sspawar
Fri, 08/03/2012 - 09:52
Permalink
1. The EVM Techniques is
1. The EVM Techniques is established using the WBS and its associated Control Accounts.
2. The Control Account also has a unique identifier that is linked to the organization’s accounting system, sometimes known as a CHART OF ACCOUNT.
3.WBS should be completed early in the project to help estimate the costs.
4. The following 3 additional tools can be used to predict the potential financial performance of the project’s product, service, or result.-ROI, Discounted Cash Flow(NPV), PAYBACK Analysis
5. A project’s cost performance baseline has a/an S-Curve shape.
6. Report Performance entails providing the information in the correct format to the right audience in a timely manner.
7. What is the communication channel formula? n(n-1)/2, where n is total numbers of persons involved
8. The lines that connect the communication nodes are also known as Channels
9. The Plan Communications addresses the communication needs of the project SH.
10. What is a PMB? Performance Measurements Baselines
sspawar
Sat, 08/04/2012 - 12:03
Permalink
I understand many fills may
I understand many fill in the blanks may not be the true answer but partly those are relevant to the subject stated. Its not at once possible but go back to treasure and bring out some matching is only the way. It is good way to learn facts like these. I try and believe to reply / attempt all by guess rather to leave on doubt or not known.