How the hell did he crash this project?
Submitted by aliweb on Sun, 08/19/2012 - 02:29
The following question (see image below) is from Farndale's 262 free questions. I can't seem to understand how come the answer is C.
According to the explanation given he is crashing activity START and D thus saving $13000. But how the hell did he come up with that? He is asking "what is the least cost to crash the schedule to 10 days" and for that he is adding "Normal Duration" + "Crashed Duration" of both START and D activities to come up with 10 days!??
Forums:


mvpmpwannabe
Sun, 08/19/2012 - 03:20
Permalink
I believe the answer is
I believe the answer is because you want to crash an activity (activities) on the critical path. The critical path is start, B, D, end and equals 12 days. To "crash" to 10 days, you need to look at one or more of these three activities. The least expensive, and gets you to 10 days, is crashing Start (saves 1 day/cost$8000) and D (saves 1 day/cost$$5000) for a total savings of 2 days at a cost of $13000. I believe Rita says to crash the activity closest to the end to help ensure meeting your completion date. I'm still studying tho so hopefully someone can confirm my thoughts or correct me. Good luck on your studies!
sspawar
Sun, 08/19/2012 - 05:46
Permalink
Its OK
DURATION
POSSIBLE
DURATION
AFTER
CRASHING
COST OF CRASHING DAYS
POSSIBLE CRASHING
DAYS
DAYS @ MINI COST
2,1@80004,3@5000aliweb
Sun, 08/19/2012 - 09:14
Permalink
But the question says "crash
But the question says "crash the schedule to 10 days" and task START and D will only save 2 days. I am not been able to understand this part.
Total normal duration is 24 days while Total crash duration is 17 days which means even if we crash all activities we will only say 7 days!?
sspawar
Sun, 08/19/2012 - 10:29
Permalink
prepare network diagram
prepare network diagram according to conditon given.
dont add simplya+b+c +------
see in detai again
2,1@80004,3@5000aliweb
Sun, 08/19/2012 - 11:28
Permalink
Oh yes now I got it!I didn't
Oh yes now I got it!
I didn't realize about network diagram and was just looking at the table to crash activities. Thanks for the explanation.
chullan88
Tue, 07/01/2014 - 06:43
Permalink
Why can't activity B be
Why can't activity B be crashed?
It has the least cost..
Any explanations...
cssk
Tue, 07/01/2014 - 19:35
Permalink
Activity B costs 12k$ and
Activity B costs 12k$ and gives you two days...I would say B is the correct answer!
chullan88
Thu, 07/03/2014 - 10:39
Permalink
Hi cssk,
Hi cssk,
I understood the question later.
The point to be remembered is that after crashing,there shouldn't be any path with duration greater than 10.
That's why B cannot be the answer.