Can somebody answer and explain?


Which of the following does not reflect two inputs to the process Control Scope that are considered something planned?
A. Project plan and Work performance Information

B. Requirements traceability matrix and Requirements documentation

C. Project plan and Requirements traceability matrix

D. Project plan and Requirements documentation
 

I think, Ans is D. Since Work Performance Information and Requirements traceability matrix are controlling process and not planned.


 


 

As per me RPS, the answer should be "B".


 


Since the rest talks about Project Plan or PMP which is NOT an input nor an output of any planning process, except Plan Risk Responses where PMP updates is an output.


 


Warmly, KK...

Actually this question is from INSITE.VELOCITEACH, free 25 questions,


answer with explanation is there , I am unable to understand.


secondly , I want suggestions guidance from  - 4Ps/5Ps recent passouts , they should partcipate in solving the problems.


I abserved few even after passing their exam, just put their long LL and disappeared.


I expect their quality participation.


Answer is A


and explanation is:


WPI , an input to this process, is not a planned input, but an actual input - providing information about the creation of the project deliverables from Direct and Management Project Execution process.