Cost Formula Difference


Hi, I notice Estimate at Completion formula difference.

 

In Rita Mulcahy book ( pg 242 ) a variation of EAC is listed as:

‘AC+[(BAC-EV)/(Cumulative CPI + Cumulative SPI)]

 

In PMBOK (Pg. 185 )  this is listed as:

‘AC+[(BAC-EV)/(Cumulative CPI * Cumulative SPI)]

 

I assume the PMBOK formula is the most accurate. Can someone verify this?

Thanks

AC+[(BAC-EV)/(Cumulative CPI * Cumulative SPI)] is the correct formula

The PMP Guru's picture

RITA Corrected this in her new Errata sheet on her site.

There are also some other small mistakes that's in the First Ver of the Sixth Edition has been higlighted in the errata.

Kind regards,

The PMP Guru.