PMPQ sample question
Submitted by pmtraining2012 on Sun, 04/07/2013 - 20:04
This is a question included in PMPQ Lite version:
The current project performance report indicates that the schedule performance index (SPI) is 1.25. This information indicates that the project is:
A) Ahead of schedule
B) Behind schedule
C) Performing poorly with respect to the schedule
D) 25% behind schedule
To see the answer go to www.pmtraining.es/PMPQeng.htm, try PMPQ Lite, and go to question number 3 of Time Management (Knowledge Areas section).
Forums:


sangc (not verified)
Sun, 04/07/2013 - 21:33
Permalink
A) Ahead of schedule
A) Ahead of schedule
admin
Tue, 04/09/2013 - 04:37
Permalink
Question is too simple for
Question is too simple for someone to click your link. Try to provide questions which are of value to readers here.
pmtraining2012
Sat, 04/20/2013 - 12:04
Permalink
Thank you
Thank you for your advice, PMZilla Admin.
You are right, the question is easy, but in the real exam there are easy questions too.
Best regards