what is the correct answer
Submitted by vivek919 on Thu, 04/11/2013 - 05:27
|
A process in a mobile phone manufacturing project has an upper control limit of 0.12. What is the standard deviation of the process if the upper control limit is set at 3 Sigma?
|
Correct answer is B. I don't understand how they calculated?
3 Sigma = 0.12, therefore, the Sigma or the standard deviation = 0.4
It shd be .04 not .4 right?
Can somebody explain?