project selection
Submitted by vijayavadrevu on Sat, 04/20/2013 - 12:02
Based on the information provided below, which project would you recommend for being pursued?
Project I, with BCR (Benefit Cost ratio) of 1:1.6;
Project II, with NPV of US $ 500,000;
Project III, with IRR (Internal rate of return) of 15%
Project IV, with opportunity cost of US $ 500,000.
A. Project I
B. Project III
C. Either Project II or IV
D. Can not say from the data provided
I have selected ( D ) where as the answer is given as option ( B )
Can someone explain as to how can a project be selected based on given input of 15% IRR alone?
Forums:


Hemant Tandon
Sun, 04/21/2013 - 02:00
Permalink
Points to
Points to remember:-
vijayavadrevu
Sun, 04/21/2013 - 05:37
Permalink
Thank you very much for your
Thank you very much for your explanation.
Can we say that,
IRR of 15% implies that for for Rs 100/ - invested, the return is Rs 115/-. Hence project 3 can be selected
NPV > 0 and hence Project 2 can be selected
Is my understanding right?
Regards
Vijaya
Hemant Tandon
Sun, 04/21/2013 - 18:00
Permalink
I can partially answer your
I can partially answer your question. NPV part is simple to explain:-
Apart from this, refer the below link which explains how to calculate the IRR of different projects.
cnpatilpmp2012 (not verified)
Sun, 04/21/2013 - 17:41
Permalink
Between NPV & IRR, always IRR
The option B (project 3 ) is correct because we need to percieve between NPV and IRR as other two options are not appropriate or doesn't make any sense. Between NPV and IRR , IRR is best option to select, unless you have option with all NPVs and bigger value to be selected..
Regards
CN Patil
sspawar
Sun, 04/21/2013 - 23:04
Permalink
other trickQ asking choose
other trick
Q asking choose only one project
option A is wrong
only B have one project
C have 2 project but have to reccomend only 1.
D have none project
hence B is correct
refer http://pmzilla.com/irr-vs-npv
Regards