Secondary Risk is basically an accepted risk after the risk response which is tolerable to the Organization.
However in case of secondary risk becomes intolerable and significant, then fall back plan has to be resorted from the Contingency allocated for such activity
bkthakkar
Mon, 04/22/2013 - 09:39
Permalink
Secondary Risk is basically
Secondary Risk is basically an accepted risk after the risk response which is tolerable to the Organization.
However in case of secondary risk becomes intolerable and significant, then fall back plan has to be resorted from the Contingency allocated for such activity
abdsal
Mon, 04/22/2013 - 10:48
Permalink
Dear thakkar, thank
Dear thakkar,
thank you!!!
abdsal
Geethika
Mon, 04/22/2013 - 12:53
Permalink
Secondary risk - iterative way?
Secondary risk is a new risk emerged out of any risk response plan implementation.
Shouldn't it be treated iteratively into risk analysis processes and develop a response for it?
We have "contingency plans", if it fails "fallback plans" made for residual risks (actively accepted)
Pls correct me if am wrong
sspawar
Mon, 04/22/2013 - 15:46
Permalink
11.5.2 is indicating for
11.5.2 is indicating for response review.