PMP question - problem solving
Submitted by siddus on Mon, 04/29/2013 - 07:05
A project manager had a complex problem to solve and made a decision about what needed to
be done. A few months later, the problem resurfaced. What did the project manager MOST likely
NOT do?
A. Proper risk analysis
B. Confirm the decision solved the problem
C. Have the project sponsor validate the decision
D. Use an Ishikawa diagram
Please explain your answers.
Thanks.
Forums:


ritusri
Mon, 04/29/2013 - 09:39
Permalink
My View
I think answer should be B. Confirm the decision solved the problem.
siddus
Mon, 04/29/2013 - 09:48
Permalink
Hi, thanks for your reply.
Hi, thanks for your reply. Your answer is correct. Can you please explain your reasoning. I opted option D assuming that the PM had not found the root cause of the problem. Therefore, when the decision was implemented the problem was temporarily fixed, but since the actual cause was not addressed, it resurfaced again after a few months.
starpmo
Mon, 04/29/2013 - 10:02
Permalink
explain
please explain the answer !!
sspawar
Tue, 04/30/2013 - 03:19
Permalink
I think B, involve all
I think B, involves all possibility.
whereas D is very specific.
it is not necessary , every problem needs ishikawa.
mlmPMP2013
Tue, 04/30/2013 - 02:14
Permalink
If a problem resurfaces then
If a problem resurfaces then originally the PM didn't confirm if that decision solved the problem (i.e. solve the root cause). Using an Ishikawa diagram is just one way to find the root cause, there are others, so you had to select the more general answer. Also even if the PM used an Ishikawa diagram, if he/she does confirm she has solved the problem it could resurface still.
siddus
Tue, 04/30/2013 - 05:27
Permalink
thanks thats a solid
thanks thats a solid argument.
PMP Fighter
Wed, 06/04/2014 - 08:24
Permalink
I also get wrong on this
I also get wrong on this question of RITA, i search on google to find this post.
I always think RITA fast track always having answer with confusion.