project close out
Submitted by vijayavadrevu on Sat, 05/18/2013 - 10:57
In functional organization who among the following is responsible for Project Close-out
A)Project Manager
B)Functional Manager
C)Project Sponsor
D)Project Stakeholder
Forums:


BK
Sat, 05/18/2013 - 11:14
Permalink
B. as Functional manager is
B. as Functional manager is PM.
cnppmp
Sat, 05/18/2013 - 11:26
Permalink
Functional Organization
Functional organization, the project manager role is limited to project expeditor, so he would be working as assisting to manager responsible for manager, so it should be functional manager. Also, project do not have authority to assign resource, no decision making authority, no authority to sue budget..
But little tricky question..
Regards
CN Patil
vijayavadrevu
Sat, 05/18/2013 - 11:29
Permalink
Yes, Thank You for the
Yes, Thank You for the explanation. Functional Manager is right. I have answered as Project manager, which is a wrong option