risk identification process
Submitted by vijayavadrevu on Sun, 05/19/2013 - 06:59
A project review by project office identifies that a particular project team has completed the risk identification process without considering the project network diagram. Which of the following is the most likely outcome under this situation?
A)Schedule risks are missed
B)Resource risks are missed
C)Cost risks are missed
D)Activity convergence risks are missed
Forums:


BK
Sun, 05/19/2013 - 07:13
Permalink
D? Cause Network diagram
D? Cause Network diagram shows Activity convergence
vijayavadrevu
Sun, 05/19/2013 - 07:18
Permalink
Yes, correct. Is your
Yes, correct. Is your analysis based on Path Convergence concept explained in PMBOK?
BK
Sun, 05/19/2013 - 07:43
Permalink
see..the qn is asking they
see..the qn is asking they missed Network diagram...so as the option given it should be path convergence.
You can refer Pmbok too..
cnppmp
Sun, 05/19/2013 - 08:59
Permalink
D
D ?
Path convergence is factor for potential risk, even Monte Carlo analysis also considers the path convergence (Critical path).
The others also have influence but the appropriate answer ofr the project network diagram would be path convergence. Hope I'm correct
Regards
CN Patil
vijayavadrevu
Sun, 05/19/2013 - 11:06
Permalink
Thanks to both BK and Patil,
Thanks to both BK and Patil, for providing good explanations