project closure

During project closure the project manager reviews

A)prior phase documentation, customer acceptance documentation, The contract

B)prior phase documentation, customer acceptance documentation, Lesson Learnt Document

C)prior phase documentation, customer acceptance documentation and deliverables

D)prior phase documentation, customer acceptance documentation and Teams Appraisal forms

 

 

 

A. This is given on pg 102 of PMBOK4.

Regards.

 

You are right

cnppmp's picture

B


Inputs for project closure is, project management plan, OPA, and acepted deliverables..


prior phase documentation = project plan


customer acceptance doc= accepted deliverables


leasson Learnt document = OPA


Regards


CN Patil

Thank you

 

What is the official answer, please tell?

 

Regards.

 

Please refer to this, the explanation given is as follws:

"

During project closure the project manager reviews prior phase documentation, customer acceptance documentation from the Verify Scope process and the contract (if applicable), to ensure that all project requirements are complete prior to finalizing the closure of the project"

 I am surprised with Answer A , BUT PMBOK super-cedes everything

 As per PMBOK page 102, option A is right. Please refer to Project or Phase Closure Documents under OPA updates