plan risk response
Submitted by vijayavadrevu on Mon, 05/20/2013 - 17:49
You are developing a risk response plan. However, every time you come up with a risk response plan, another risk is identified caused by the response. What should be your BEST approach?
A)Make a documentation of the new risk events and carry on with the Plan Risk Responses process
B)Try to understand the project work better
C)Dedicate some more time in so that the risk responses are clearly defined
D)Get more members and stakeholders in identification of risk process as you missed certain risks
Forums:


sanskrit
Tue, 05/21/2013 - 00:22
Permalink
A
A
cnppmp
Tue, 05/21/2013 - 06:51
Permalink
A
A
Rgrds
CNP
vijayavadrevu
Tue, 05/21/2013 - 09:40
Permalink
A is correct. Why can't it be
A is correct. Why can't it be D? Is it because we are talking about Plan Risk Response Process and D is about Identify risks and not risk updates?