project selection methods

A)

B)

C) Constrained optimization methods

D)None of the above

C : Constrained optimization methods 

 The answer is given as C where as in the e-references of PMI.org, scoring models and economic models come under benefit measurement methods

 

Need clarification

 

 

 

regarding to rita page 107  economic models come under benefit measurement methods

so the correct answer should be B

 B) Benefit Measurement Method

cnppmp's picture

Both are for the Benefit measurement methods, then it that case it should be D?


In RITA's book it says Benefit Measurement method and Comparative Approach (method).


Regards


CNP