time estimate
Submitted by vijayavadrevu on Fri, 05/24/2013 - 10:00
The table given below shows the time estimates for different tasks. Please refer to it and answer the question that follows.
1) What is the impact on the project if task 1->2 takes 2 months more than what was earlier planned?
- The project duration will increase by 1 month
- The project risk will increase
- The project duration will increase by 2 months
- The project float will increase by 2 months
Forums:


san
Fri, 05/24/2013 - 11:51
Permalink
Initially there is one
Initially there is one Critical path i.e Start -4-5-End with 12 days duration.
If task 1->2 days takes 2 months more means the duarion of path increases from 10 to 12 days(start 1-2-End)
Since no of critical paths are increased the risk will increase. Answer should be 2.
Thanks
vijayavadrevu
Fri, 05/24/2013 - 18:01
Permalink
True. Risk will increase as
True. Risk will increase as delay in either of the critical paths will cause a delay in the project