 Your bank is launching an advertisement campaign for a new product. You have been instructed by the project sponsor to complete some milestones with the available skilled resources. From a project management perspective, this is: 


1.    

Constraint


2.    

Assumption


3.    

Discretionary dependency


4.    

Mandatory dependency

Constriants.  As per PMbok ,Constraints are delivery dates,policies , available skill resources (169 page)

 Yes, constraints is the right answer. It is available in page 148 of PMBOK under Inputs of Estimate Activity Durations  (also)

 1 constraints