Cost performance baseline is referred

In the earned value management technique, the cost performance baseline is referred to as:

  1. Cost Measurement Baseline (CMB)

  2. Performance Measurement Baseline (PMB)

  3. Performance Base Value (PBV)

  4. Performance Cost Baseline (PCB)

 In the earned value management technique, the cost performance baseline is referred to as Performance Measurement Baseline (PMB)

Sometimes, Total PV is also called PMB

(pmbok 178,182)

Thanks again, Geethika.

 B: Performance Measurement Baseline (PMB)