PMstudy with Rita regarding Risk identification
Submitted by y0zh on Sat, 05/25/2013 - 13:52
| Question No : 133 |
||
| As a project manager, you understand the importance of identifying and documenting project risks. In this context, which of the following statements is true? |
||
| Choice 1 | Risk identification occurs during the Planning of the project | |
| Choice 2 | Risk identification occurs during Monitoring and Controlling of the project | |
| Choice 3 | Risk identification occurs during Execution of the project | |
| Choice 4 | Risk identification occurs during different project stages depending on the type of the project | |
| Correct Choice : 1 | ||
| Justification : |
||
| Risk identification is done as part of the Planning Process Group | ||
As I remeber, Rita's book says that Risks may be identified within whole project life cycle, not only planning. Have I missed something? Please advise
Forums:


sanskrit
Sat, 05/25/2013 - 15:03
Permalink
Both are right (Rita as well as this answer)
Choice 1 : Is the only one thats is correct among the AVAILABLE option
I think your question is why not Choice 4 ?
The way I will explain the reason choice 4 is wrong is risk identification process group does NOT depends on the type of the project.