Total cost of the Project
Submitted by MANOJ RAMRAOJI ... on Tue, 06/04/2013 - 16:09
PM has budgeted the total cost of the project by considering the aggregated cost of each element required and ______ costs.
1) Unknown known AND known unknown
2) Known Unknown AND unknown unknown
3) Known known AND unknown unknown
4) unknown unknown AND unknown known
Forums:


cnppmp
Tue, 06/04/2013 - 16:20
Permalink
Option2
Option2: Known / Unknown stands for Contingency reserve and Unknown / Unknown stands for managemnt reserve
Regards
CN Patil