Process group question
Submitted by Nagendra on Thu, 07/04/2013 - 17:21
uestion :
Your team is churning out high level design for the project. Which process group are you in?
Answers :
Initiation Phase
Planning Phase
Executing
Acquisition Phase
Correct Answer: Option 3
Explanation: Correct option is C
I think HLDs are prepared in Initiation. can anyone comment?
Forums:


admin
Fri, 07/05/2013 - 04:10
Permalink
In order for you to start
In order for you to start HLD you should have completed requiremetns, to complete requiremetns, you should have a project plan and team in place, This is not possible during initiation phase, neither during planning.
Hope that helps