Response to Negative Risks
Submitted by elthox on Mon, 07/08/2013 - 19:37
When a negative risk occurs in a project, a response to it would be called:
-
A contingency plan
-
Failure planning
-
A workaround
-
Backup planning
I selected A, as per Scordo`s answers it is C.
Explanation: A workaround is a response to a negative risk that has occurred. It differs from a contingency plan in that a workaround is not planned in advance of the occurrence of the risk event.
The question doesnt mention about planned or unplanned responses.
What do you think?
Forums:


admin
Tue, 07/09/2013 - 03:49
Permalink
Yes, but since it says a
Yes, but since it says a negative risk has occured, we can assume that it was on the risk register. I agree tha there is ambiguity in the question.
humanbeing2001
Tue, 07/09/2013 - 04:54
Permalink
A negative risk can not occur
A negative risk can not occur if there is contingency plan in place. If the Question had been "A negative Risk can occur in a project, a response to it would be called Contingency Plan." Once we have contingency plan in place, a negative risk can not occur as contingency plan would response to it prior to its occuring.
Once a negative risk occurs in a project, it means that there were no contingency plan in place and now we have to deal with it either with Workaround or fallback plan.